| Generation Interconnection Number | Nearest Town or County | State |
CA | In-Service Date (proposed) | CAPACITY (MW) | Type | STATUS | Expected Completion Date | Reason for Delay |
| LGE-GIS-2007-001 |
Central City |
KY |
LGEE |
1/12/2015
|
750.0 |
Steam |
WITHDRAWN |
|
|
| LGE-GIS-2007-002 |
Central City |
KY |
LGEE |
1/12/2016
|
610.0 |
Combined Cycle |
WITHDRAWN |
|
|
| LGE-GIS-2007-003 |
Henderson County |
KY |
LGEE |
3/31/2011
|
640.0 |
Combined Cycle |
WITHDRAWN |
|
|
| LGE-GIS-2007-004 |
Henderson County |
KY |
LGEE |
3/31/2011
|
640.0 |
Coal/ gasification |
WITHDRAWN |
|
POI, Study process |
| LGE-GIS-2008-001 |
Wise County |
VA |
EON |
12/1/2011
|
128.8 |
Wind |
FACILITY STUDY IN PROGRESS |
|
|
| LGE-GIS-2008-002 |
Ohio county |
KY |
LGEE |
8/1/2010
|
5.4 |
Small Gen Synchronous |
WITHDRAWN |
|
|
| LGE-GIS-2008-003 |
Sulphur |
KY |
LGEE |
8/1/2010
|
9.0 |
Small Gen Synchronous |
WITHDRAWN |
|
|
| LGE-GIS-2008-004 |
Stanford |
KY |
LGEE |
8/1/2010
|
5.4 |
Small Gen Synchronous |
WITHDRAWN |
|
|
| LGE-GIS-2009-001 |
Paducah |
KY |
LGEE |
5/1/2010
|
123.4 |
Pratt & Whitney FT-8 Swift Pacs |
IMPACT STUDY COMPLETED |
|
|
| LGE-GIS-2009-002 |
Central City |
KY |
LGEE |
4/1/2017
|
560.0 |
Combined Cycle Gas |
WITHDRAWN |
|
|
| LGE-GIS-2009-003 |
Central City |
KY |
EON |
4/1/2017
|
690.0 |
Combustion turbine/ steam |
WITHDRAWN |
|
N/A |
| LGE-GIS-2009-004 |
Bedford |
KY |
E.ON |
10/1/2010
|
35.0 |
Steam Turbine |
IMPACT STUDY COMPLETED |
|
|
| LGE-GIS-2010-001 |
Louisville |
KY |
EON |
6/1/2015
|
690.0 |
Combustion turbine/ steam |
FEASIBILITY STUDY IN PROGRESS |
|
|
| LGE-GIS-2010-002 |
LOUISVILLE |
KY |
LGEE/KU |
6/1/2016
|
704.0 |
2 X 1 COMBINED CYCLE |
FEASIBILITY STUDY IN PROGRESS |
|
backlog of prior queue projects |
| LGE-GIS-2010-003 |
Central City |
KY |
LG&E/KU |
1/1/2016
|
690.0 |
Combustion turbine/steam |
None |
|
|
| LGE-GIS-2011-001 |
Buckner |
KY |
LG&E/KU |
1/1/2015
|
450.0 |
Combustion Turbine |
FEASIBILITY STUDY IN PROGRESS |
|
|
| LGE-GIS-2011-002 |
Louisville |
KY |
LG&E | KU |
6/1/2015
|
75.0 |
Combustion turbine/steam |
None |
|
|
| LGE-GIS-2011-003 |
Louisville |
KY |
LG&E | KU |
1/1/2012
|
21.0 |
Hydro |
None |
|
|
| LGE-GIS-2011-004 |
Harrodsburg |
KY |
LG&E | KU |
1/1/2018
|
915.0 |
Combustion turbine/steam |
None |
|
|
| LGE-GIS-2011-005 |
Harrodsburg |
KY |
LG&E | KU |
3/30/2012
|
6.3 |
Hydro |
FEASIBILITY STUDY REQUESTED |
|
|